IB Wall Detail Fully Adhered

To install an adhered wall base flashing, you will first need to terminate the membrane at the roof-to-wall transition. Locate fasteners 12 inches in the center. Measure the dimensions of the wall, and cut the membrane into manageable lengths to install in a vertical or horizontal fashion. Ensure to allow for the base flashing to extend a minimum of five inches out onto the roof, extending past the membrane termination and for a sufficient distance to form a one-and-a-half-inch welded seam. Apply IB Vertibond Adhesive to the wall and to the backside of the membrane in accordance with the manufacturer's instructions using a roller or squeegee at the specified rate. Allow the adhesive to become tacky before applying the membrane to the substrate.

Place in position by starting on the top and carefully setting it into place. Apply pressure and work from top to bottom to remove any wrinkles, air pockets, and/or voids. Use a soft brush or broom to ensure full contact is made with the substrate. Weld the base seems to form a one-and-a-half-inch welded seam past the fastener plate. Upon completing the installation, ensure all seams and laps are inspected and probed. If deficiencies are found, the area must be re-welded or repaired.

 

Ready to Discuss Your Project?

Are you a commercial building owner or property manager and have some questions about products or specifications? Let us know and one of our team members will be in touch to help answer your questions.

Review my Project